Kindergarten construction in Kobuleti delayed for years

Transparency International Georgia has found that the construction of kindergartens in villages of Kobuleti Municipality dragged on for years, while the funds allocated for construction periodically increased significantly:
- Kobuleti Municipality failed to manage the construction of kindergartens in three villages (Khala, Gvara, Kveda Kvirike). It failed to prepare design and cost-estimate documents of adequate quality and failed to supervise the works in a timely and effective manner. Ultimately, this made the project's GEL 2,117,523 more expensive;
- In the village of Khala, construction was completed in December 2024, almost four years behind the original deadline, and GEL 221,422 more was spent than the original budget;
- In the village of Gvara, works were completed three years late, in July 2025 instead of 2022, and GEL 1,008,814 more was spent than the original budget;
- In the village of Kveda Kvirike, completion of construction is planned for November 2026, four years late. The kindergarten here was supposed to be completed in September 2022. Over this period, construction costs increased by an additional GEL 887,287;
- Before construction was completed, the contracts for all three kindergartens were amended 43 times in total;
- The same pattern emerged in all three tenders: a company initially wins the procurement, partially carries out the work, receives part of the contract amount as an advance payment and stops work; when a new tender is announced, the contract amount increases. In the case of the Khala kindergarten, the partnership "Nika" acted this way, receiving GEL 1,160,566 as an advance (85% of the total contract value). In the cases of Gvara and Kveda Kvirike, it was Build Management LLC, which received GEL 149,487 and GEL 271,458 in advances, respectively;
- Notably, the fourth electronic tender announced for the construction of the Gvara kindergarten was won without competition by "Gza", a company of businessman Giorgi Chkonia, who was elected from "Georgian Dream" as Kobuleti's delegate to Georgia's illegitimate parliament. Today the company is owned by Giorgi Chkonia's daughters.
Khala
In the village of Khala, kindergarten construction was completed in December 2024 instead of March 2021. The contract was amended 17 times; nevertheless, the company that won the first tender still failed to complete the works, and another tender was announced to complete the remaining works. In total, GEL 221,422 more was spent.
The first electronic tender was announced on 31 January 2020 and closed on 2 March, with an estimated procurement value of GEL 1,588,921.
In the first electronic tender, the partnership "Nika" offered the lowest price, and on 7 April 2020 a contract was signed with it for GEL 1,357,545. Under this contract, the supplier undertook that the village of Khala would have a new kindergarten from March 2021. The parties amended the contract 17 times, both in terms of design and cost estimates and in terms of completion deadlines, but the supplier still failed to fulfil its contractual obligations. On 3 October 2023, the contracting authority unilaterally terminated the contract and imposed a penalty of GEL 185,014. Before the unilateral termination, the supplier had already received 85% of the total contract value, i.e. GEL 1,160,566.
To complete the remaining construction works, a new electronic tender was announced. Following the disqualification of a competitor, it was won by Bza LLC, with which a contract worth GEL 418,401 was signed on 7 March 2024. The supplier fulfilled its contractual obligations on 10 December 2024.
Gvara
In the village of Gvara, kindergarten construction was completed in July 2025 instead of September 2022, and GEL 1,008,814 more than planned was spent on it. The kindergarten construction tender was won without competition by "Gza", a company owned by Giorgi Chkonia, a member of Georgia's illegitimate parliament. Transparency International Georgia has published several studies on the company's benefits from public procurement.
According to the first electronic tender for the kindergarten construction works, the estimated procurement value was GEL 1,515,040. No bidder took part in it, so this electronic tender did not take place.
In the repeat electronic tender announced on the same terms, which closed on 31 August 2021, Build Management LLC won and received a contract for GEL 1,408,983. The company was to complete the construction of the Gvara kindergarten by September 2022. The parties amended the contract 3 times, but the supplier still failed to ensure timely performance. As a result, on 27 December 2022, the contracting authority unilaterally terminated the contract and imposed a penalty of GEL 266,398. By that time, the contracting authority had already paid 11% of the value of the works performed, i.e. GEL 149,487.
In the new electronic tender to procure the remaining construction works, again no one took part, and the tender failed. One week after the failed tender, a new electronic tender was announced with an estimated procurement value of GEL 2,065,000. It was won without competition and without any price reduction by Gza LLC, the company of Giorgi Chkonia, a member of the illegitimate parliament and a major donor to "Georgian Dream". The contract with it was signed on 24 November 2023. Gza LLC undertook to complete construction of the new kindergarten by April 2025. The parties amended this contract too, and once again postponed the completion deadline. Specifically, the contract value was increased by GEL 203,310, and 11 July 2025 was set as the final deadline for completing the works.
Kveda Kvirike
In the village of Kveda Kvirike, kindergarten construction is due to be completed in November 2026 instead of September 2022, and GEL 887,287 more than planned is being spent on it.
In the first electronic tender, with an estimated procurement value of GEL 1,635,748, no bidder took part, and the tender failed.
The repeat electronic tender, on unchanged terms, closed on 31 August 2021, and here too Build Management LLC won. The company received a contract worth GEL 1,521,239 and was to hand the kindergarten over to the municipality by September 2022. The completion deadline was postponed, but Build Management still failed to complete the project. On 27 December 2022, the municipality unilaterally terminated the contract and imposed a penalty of GEL 247,275 on the company. The contracting authority had already paid 18% of the total contract value, i.e. GEL 271,458.
A new electronic tender failed again because no one took part. One day after the failed tender, on 30 August 2023, yet another electronic tender was announced, with an estimated procurement value of GEL 1,999,000. One company took part, Mshenebeli 2016 LLC, which failed to submit documents proving its experience and a cost estimate. It was therefore disqualified. Three days after the tender ended unsuccessfully, the fifth electronic tender was announced on unchanged terms. It again ended without result on 26 October 2023, as no bidder took part.
The sixth electronic tender proved successful. It closed on 5 December 2023 and was won without competition by Mshenebeli LLC, which had donated GEL 15,000 to "Georgian Dream" in 2021. The company undertook to complete the kindergarten by May 2025 and in return receive the contract amount of GEL 1,949,889. This contract was amended 16 times: the contract value was increased by GEL 187,179 and the term was extended by 18 months. The supplier was paid GEL 603,500 in total in advance payments, in 4 installments. Construction of the kindergarten is due to be completed on 28 November this year.